单项选择题

Your environment includes a Windows Server 2008 R2 Hyper-V failover cluster. You manage the virtual environment by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2.  You plan to perform maintenance on the Hyper-V failover cluster. You need to complete the maintenance on the failover cluster while maximizing the uptime of the virtual machines (VMs). 
What should you do prior to starting maintenance on each cluster node?()

A.Use Failover Cluster Manager to pause the cluster node
B.Use Failover Cluster Manager to perform a quick migration of all VMs to another cluster node
C.Use VMM to place the cluster node in maintenance mode
D.Use VMM to pause all VMs and move them to another cluster node


您可能感兴趣的试卷

你可能感兴趣的试题

2.单项选择题You deploy two Windows Server 2008 R2 Hyper-V servers. You manage the servers by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You need to ensure that you can restore virtual machines (VMs) in the event of a hardware failure. What should you do?()

A.Use a PowerShell script to create a snapshot of each VM. Run the script every 60 minutes on each Hyper-V server
B.Use a PowerShell script to create a checkpoint of each VM. Run the script every 60 minutes on each Hyper-V server
C.Use a PowerShell script to pause, export, and start each VM, and then to copy the export to the opposite Hyper-V server. Run the script once per day on each Hyper-V server
D.Use a PowerShell script to shut down, export, and start each VM, and then to copy the export to the opposite Hyper-V server. Run the script once per day on each Hyper-V server

4.单项选择题

Your company has a main office in New York and branch offices in Chicago and Los Angeles. You plan to use Microsoft Application Virtualization (App-V) 4.5 with SP1. 
You install an Application Virtualization Management Server in the New York office. You need to provide application virtualization with active upgrade support in the Chicago and Los Angeles offices. You must design your App-V solution so that it minimizes WAN traffic. 
What should you do?()

A.Install Application Virtualization Streaming Servers in the Chicago and Los Angeles offices
B.Install Application Virtualization Management Servers in the Chicago and Los Angeles offices
C.Install the Application Virtualization \CONTENT folder on file shares in the Chicago and Los Angeles offices
D.Install the Application Virtualization \CONTENT folder on IIS 7 servers in the Chicago and Los Angeles offices

7.单项选择题

Your company uses Windows Server 2008 R2 Hyper-V servers to provide a Microsoft Virtual Desktop Infrastructure (VDI) environment. 
Maintenance tasks result in reduced capacity on several servers. You need to prevent servers from experiencing performance problems during maintenance. 
What should you do?()

A.Set the user logon mode on every server to Enabled
B.Create additional DNS A records for the servers, and use DNS round-robin
C.In Remote Desktop Connection Broker, assign a lower weight to the servers that will undergo maintenance
D.In Remote Desktop Connection Broker, assign a higher weight to the servers that will undergo maintenance

8.单项选择题

Client computers on your network run either Windows Vista or Windows 7. 
You plan to use Microsoft Application Virtualization (App-V) 4.5 with SP1 as an application virtualization platform. You need to virtualize applications by using mount point installations (MNT). 
What should you do?()

A.Configure the App-V Sequencer to have two partitions
B.Configure the App-V Sequencer on a Windows 7 client computer
C.Configure virtualized applications to check for updates during installation
D.On the reference computer, install all software that typically runs on client computers

9.单项选择题

Your network environment includes the following elements: Two Windows Server 2008 R2 Hyper-V serversTwo VMware ESX 3.5 serversMicrosoft System Center Virtual Machine Manager (VMM) 2008 R2  
You run several Windows Server 2003 virtual machines (VMs) on your ESX host servers. You need to convert the ESX VMs to Hyper-V, and you must minimize the downtime during the conversion. 
What should you do?()

A.Run the New-V2V PowerShell cmdlet
B.Perform a physical-to-virtual (P2V) conversion while the VMs are running
C.Shut down the VMs, and then perform a virtual-to-virtual (V2V) conversion
D.Shut down the VMs, and then perform a physical-to-virtual (P2V) conversion

10.多项选择题

Your network includes Windows Server 2008 R2 Hyper-V failover clusters that support highly available virtual machines (VMs). 
You manage virtual machines by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You are planning to deploy a large number of VMs to the failover clusters. All VMs must remain available when one node of each cluster is offline. You need to determine the best placement for the new VMs among the clusters. 
Which two actions should you perform?()

A.For each cluster, set the cluster reserve to 1
B.In each cluster, place one host server in maintenance mode
C.Determine the placement for each VM by using the data that is generated by running the Get-VMHostRating PowerShell cmdlet
D.Determine the placement for each VM by using the data that is generated by running the Get-VMPerformance PowerShell cmdlet

最新试题

You manage your existing virtual environment by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You are designing a highly available Hyper-V solution. You need to minimize the downtime of virtual machines (VMs) during maintenance periods. What are two possible ways to achieve this goal?()

题型:多项选择题

Your network includes four servers that run Windows Server 2008 R2. Each server has the network configuration shown in the following table. You are designing a Hyper-V failover cluster. You need to ensure the highest level of availability for virtual machines (VMs) that run on the cluster. What should you do?()

题型:单项选择题

Your virtual environment includes Windows Server 2008 R2 Hyper-V servers. You manage the environment by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You are planning to install an application upgrade. Testing the production application requires access to the following three virtual machines (VMs): a domain controller, a server that runs Microsoft SQL Server, and an IIS Web server.You need to test the application upgrade in a virtual environment that is isolated from the production network.Which two sets of actions should your plan include?()

题型:多项选择题

You are designing a Windows Server 2008 R2 Hyper-V environment. Your design includes a failover cluster that supports live migration. You need to ensure that the network supports this design.What should you do?()

题型:单项选择题

You plan to implement Hyper-V live migration.You configure the Hyper-V hosts to connect to a shared storage.You need to prepare the Hyper-V hosts for the implementation of live migration.What should you configure on the Hyper-V hosts?()

题型:单项选择题

You plan to deploy two virtual machines (VMs) that will be configured as nodes in a failover cluster. The VMs will run file and print services. You need to recommend a storage solution for the planned deployment.What should you include in the recommendation?()

题型:单项选择题

You are designing a Windows Server 2008 R2 Hyper-V Virtualization environment. Your host servers must have the following elements:- A dedicated management network adapter.- A dedicated virtual network for child iSCSI network traffic.- A dedicated virtual network for child network traffic with VLAN tagging. You need to choose adapters that minimize the host server processing.Which adapters should you choose?()

题型:单项选择题

Your network contains five unused Hyper-V hosts. The unused Hyper-V hosts are configured as shown in the following table.You need to identify which two servers can be used to create a Hyper-V host cluster. The Hyper-V cluster must support Hyper-V live migration. Which servers should you identify?To answer, drag the appropriate servers to the correct Hyper-V host cluster in the answer area.

题型:问答题

Your network contains four computers. The computers are configured as shown in the following table:You plan to deploy the following:-Four Hyper-V servers that run Windows Server 2008 R2 Service Pack l (SP1)-One server that has Microsoft System Center Virtual Machine Manager 2008 R2 installedYou need to recommend a solution to perform physical-to-virtual machine (P2V) conversions of the computers. The solution must minimize downtime on the computers. What should you recommend?To answer, drag the appropriate conversion type to the correct computer in the answer area.

题型:问答题

Your company has a main office and 10 branch offices. The main office has a firewall. All connections from the branch office are sent through the firewall.Each office has two Hyper-V hosts that run Windows Server 2008 R2 Service Pack 1 (SP1). Each host contains 10 virtual machines (VMs).You deploy Microsoft System Center Virtual Machine Manager 2008 R2 in the main office.You need to recommend changes to the firewall to ensure that branch office administrators can manage their local Hyper-V hosts by using System Center Virtual Machine Manager. The solution must ensure that only the required ports are opened.Which firewall ports should you recommend opening?()

题型:多项选择题