You have a two-node Hyper-V failover cluster that uses SAN storage. You are designing storage for a new virtualization environment by using Windows Server 2008 R2. 
You plan to deploy five virtual machines (VMs) per logical unit number (LUN). You need to be able to perform a live migration of a single VM while the other VMs continue to run on the host server. 
What should you do?()

A.Use Cluster Shared Volumes (CSVs)
B.Use fixed disks on the SAN storage
C.Boot the virtual machines from iSCSI LUNs
D.Use dynamically expanding disks on an iSCSI LUN


您可能感兴趣的试卷

你可能感兴趣的试题

2.单项选择题

You are designing a Windows Server 2008 R2 Hyper-V environment. You need to be able to dynamically assign new storage to Windows virtual machines (VMs). 
What should you do?()

A.Use fixed virtual hard disks (VHDs)
B.Install Hyper-V Integration Services on the VMs
C.Install the VMs in Cluster Shared Volumes (CSVs)
D.Use dynamically expanding virtual hard disks (VHDs)

3.单项选择题

You are designing a Windows Server 2008 R2 Hyper-V virtualization environment. Your host servers must have the following elements: 
A dedicated management network adapter.A dedicated virtual network for child iSCSI network traffic.A dedicated virtual network for child network traffic with VLAN tagging. You need to choose adapters that minimize the host server processing. 
Which adapters should you choose?()

A.three network adapters that support 802.1p
B.two network adapters that support 802.1q, and one iSCSI host bus adapter
C.two network adapters that support 802.1p, and one network adapter that supports TCP Chimney
D.two network adapters that support 802.1q, and one network adapter that supports Jumbo frames

4.多项选择题

Your virtual environment includes Windows Server 2008 R2 Hyper-V servers. You manage the environment by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You are planning to install an application upgrade. 
Testing the production application requires access to the following three virtual machines (VMs): a domain controller, a server that runs Microsoft SQL Server, and an IIS Web server. You need to test the application upgrade in a virtual environment that is isolated from the production network. 
Which two sets of actions should your plan include?()

A.Pause the three VMs, and copy the .vhd files to the test environment
B.Create a checkpoint of the three VMs, and export the checkpoint to the test environment
C.Import the checkpoint into the test environment, and apply the application update for testing
D.Create three VMs in the test environment, attach the existing .vhd files, and apply the application update for testing

5.单项选择题You are planning to deploy two Windows Server 2008 R2 Hyper-V servers. You need to design the storage of VHD files for maximum security. What should you do?()

A.Store the VHD files on a dedicated NTFS volume
B.Store unencrypted VHD files on a volume that uses Windows BitLocker drive encryption
C.Encrypt the VHD files by using EFS on a volume that uses Windows BitLocker drive encryption
D.Encrypt the VHD files by using EFS on a volume that does not use Windows BitLocker drive encryption

9.单项选择题

Your network includes Windows Server 2008 R2 Hyper-V servers. Each Hyper-V server runs multiple virtual machines (VMs). You need to detect performance issues and generate an alert when Hyper-V server load exceeds specific thresholds. 
Which tool should you use?()

A.Microsoft System Center Capacity Planner 2007
B.Microsoft System Center Operations Manager 2007 R2
C.Microsoft System Center Configuration Manager 2007 R2
D.Microsoft System Center Virtual Machine Manager 2008 R2

最新试题

Your network environment includes two Windows Server 2008 R2 Hyper-V servers and one VMware ESX 3.5 host server.You are designing a Microsoft System Center Virtual Machine Manager (SCVMM) 2008 R2 implementation to manage your network environment. SCVMM must be able to perform management tasks that require file transfer operations between your VMware server and your Windows servers.You need to configure the ESX host server to ensure that file transfer operations are encrypted, and follow security best practices.What should you do?()

题型:单项选择题

You plan to deploy two virtual machines (VMs) that will be configured as nodes in a failover cluster. The VMs will run file and print services. You need to recommend a storage solution for the planned deployment.What should you include in the recommendation?()

题型:单项选择题

Your network includes Windows Server 2008 R2 Hyper-V failover clusters that support highly available virtual machines (VMs). You manage virtual machines by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2.You are planning to deploy a large number of VMs to the failover clusters. All VMs must remain available when one node of each cluster is offline.You need to determine the best placement for the new VMs among the clusters.Which two actions should you perform?()

题型:多项选择题

You plan to implement Hyper-V live migration.You configure the Hyper-V hosts to connect to a shared storage.You need to prepare the Hyper-V hosts for the implementation of live migration.What should you configure on the Hyper-V hosts?()

题型:单项选择题

You plan to deploy the Virtualization technologies of Microsoft Desktop Optimization Pack (MDOP).You need to recommend a licensing solution for the planned deployment.What should you include in the recommendation?()

题型:单项选择题

Your network contains Microsoft System Center Virtual Machine Manager and 10 Hyper-V hosts. You plan to convert all of the domain controllers to virtual machines (VMs).You need to recommend a recovery solution for the domain controllers. The solution must meet the following requirements:- Prevent inconsistencies in the Active Directory database.- Provide for the recovery of accidentally deleted Active Directory objects. - Provide for recovery if an administrator incorrectly modifies system settings.What should you include in the recommendation?()

题型:单项选择题

You configure a Windows Server 2008 R2 Hyper-V server with several virtual machines (VMs). A software vendor releases a software update for an application that runs on only one of the VMs. You need to plan a strategy that enables you to install and test the update without interrupting application availability and without corrupting data.What should you do first?()

题型:单项选择题

You manage your existing virtual environment by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You are designing a highly available Hyper-V solution. You need to minimize the downtime of virtual machines (VMs) during maintenance periods. What are two possible ways to achieve this goal?()

题型:多项选择题

Your network contains four computers. The computers are configured as shown in the following table:You plan to deploy the following:-Four Hyper-V servers that run Windows Server 2008 R2 Service Pack l (SP1)-One server that has Microsoft System Center Virtual Machine Manager 2008 R2 installedYou need to recommend a solution to perform physical-to-virtual machine (P2V) conversions of the computers. The solution must minimize downtime on the computers. What should you recommend?To answer, drag the appropriate conversion type to the correct computer in the answer area.

题型:问答题

You are designing a Windows Server 2008 R2 Hyper-V environment.You need to be able to dynamically add new storage to Windows virtual machines (VMs).What should you do?()

题型:单项选择题